Module 05 · Class 20 — The Project Status Report
Valeria writes a formal project status update. Consolidate future forms and project management vocabulary in a written report.
Narrative Scene
End of Week 7 — Valeria writes the project status report
The good news: with an additional designer brought in on Monday, the team made significant progress this week. The visual identity is now at 65% — still behind, but recovering. The CEO review is still scheduled for Week 8. Tom Whitfield has asked Diego to submit a weekly project status report going forward. Diego asks Valeria to write this week’s report. It is a formal internal document that Tom will read before the call on Friday. Valeria needs to be clear, honest, and confident.
Vocabulary Language Focuson track: progressing as planned; meeting the agreed milestones at risk: not progressing as planned; there is a real possibility of missing a deadline or target mitigating action: a step taken to reduce the impact of a risk or problem revised target: a new, updated deadline or goal, set after the original one was missed or adjusted transparency: openness and honesty, especially about problems or decisions credibility: the quality of being trusted and believed by others recovery: returning to a better or normal state after a problem momentum: the force or energy behind something that is progressing well RAG status: Red / Amber / Green — a simple system to communicate project health: Red = at risk, Amber = some concerns, Green = on track recovery plan: a detailed plan to bring a delayed or troubled project back on track week-on-week: comparing progress from one week to the next project health: an overall assessment of whether a project is progressing well or has problems scope: the agreed range of work included in the project resources: the people, time, and budget available to complete a project schedule variance: the difference between the planned schedule and the current actual schedule sign-off: formal approval from the client to move to the next project phase |
RAG Status Framing
Status | Report language |
GREEN — On Track | "All milestones are on schedule. No risks to report." |
AMBER — Some Concerns | "Progress has slowed due to a resource constraint. Mitigating actions are in place. Delivery is expected by the revised target date." |
RED — At Risk | "The project is significantly delayed. The current delivery date is unlikely to be met without immediate action." |
Project Status Report — Standard Structure
Section | Content |
Project name and date | Grupo Bernal Brand Refresh | Week 7 Report | 24 January 2025 |
Overall status | AMBER — recovering; mitigating actions in place |
Progress this week | What was completed? What milestones were hit? |
Blockers / risks | What caused delays? What is still at risk? |
Actions taken | What steps were taken to address the issue? |
Next steps | What will happen next week? By whom and by when? |
Revised timeline | Are there any changes to the overall delivery date? |
Phrasal Verbs in Contextget back on track: "With the additional designer, the project is expected to get back on track by end of Week 8." (= return to the planned schedule) hand over: "The visual identity files will be handed over to the client at the Week 8 review." (= give formally or officially) wrap up: "Phase 2 is expected to wrap up by the end of Week 10, one week behind the original schedule." (= come to a conclusion/finish) |
Sample Project Status Report
PROJECT STATUS REPORT Project: Grupo Bernal Brand Refresh Report Period: Week 7 (20–24 January 2025) Prepared by: Valeria Moreno | Reviewed by: Diego Vargas --- OVERALL STATUS: AMBER
PROGRESS THIS WEEK Visual identity design: progressed from 40% to 65% completion. An additional designer was brought in on Monday to address the resource gap. Logo concept 1 was finalised. Colour palette and typography are in progress.
BLOCKERS / RISKS A resource constraint resulted in a schedule variance of approximately 1.5 weeks. If the additional designer is not available for the full duration, progress could slow again. This risk is being actively monitored.
ACTIONS TAKEN Additional resource was allocated on Monday, 20 January. A revised internal delivery plan was shared with the design team. Ana Restrepo (client) was updated directly. The Week 8 CEO review is confirmed.
NEXT STEPS Week 8: Complete visual identity (target: 100%). Deliver to client for CEO review. Week 9–10: Brand guidelines document. Revised target: Week 11 (was Week 10).
OVERALL TIMELINE The project is expected to wrap up one week later than originally planned. Final delivery: Week 12. Rollout support: Week 13. |
Analysis questions:
● Why is the status AMBER rather than RED? What evidence supports this assessment?
● Find two examples of passive voice. Why is passive used here rather than active?
● What has the schedule variance been? By how much is the project delayed overall?
● "This risk is being actively monitored" — what does this phrase communicate about accountability?
Project status reports are expected to be honest and concise. The standard structure — summary, progress, blockers, next steps — works across industries. Avoid reporting only good news: stakeholders trust reporters who flag problems early.
Practice Exercises
3 questionsNew exercises to reinforce what you learned. Different from the lesson material.
Choose will or going to_ The visual identity ___
Will vs. Going To_ I ___
Will vs. Going To-he project is ___